7292. Five bridges Conakry - Guinea / Cinq ponts - Guinée - DRIVE18GN01

On request of the RVO (Dutch Enterprise Agency), the NCEA has reviewed the ESIA for the Five link and access bridges for the city of Conakry. This advice was prepared by a working group of experts acting on behalf of the NCEA. The group comprises expertise in the following disciplines: ecology, infrastructure, social impacts and resettlement procedures. This review has been conducted based on a draft ESIA and is taking place prior to the review by the BGEEE. The draft ESIA reviewed by the NCEA does not contain a Resettlement Action Plan (RAP) or Livelihood Restoration Plan (LRP) (or combination of both)./ Sur demande du RVO, la NCEE a examiné l'EIES de la construction des 5 ponts à Conakry. Cette examen a été préparé par un groupe de travail d'experts au nom de la CNEE. Ce groupe réunit les expertises des disciplines suivantes: écologie, infrastructure, impacts sociaux et procédures de réinstallation.  Le présent examen par la CNEE, à la base d’une ébauche d’EIES, a eu lieu avant l'examen par le Bureau Guinéen d’Études et d’Évaluation Environnementale (BGEEE). Pour l'instant, l'EIES ne comprend pas de Plan d'Action de Réinstallation (PAR), ni un Plan de Restauration des Activités Économiques (PRAE).  

Rapports consultatifs et autres documents

23 nov 2018: Memorandum

Advisory Review of ESIA for 5 Link and Access Bridges Conakry

Examen de qualite EIES de 5 ponts de liaison et desenclavement Conakry

Informations importantes

The project is located in the capital city of Guinea, Conakry. The main objective of this project is to improve accessibility of the city of Conakry with the construction of five bridges and improvement of their linked roads. Four of these bridges are planned in the Conakry Prefecture namely: Kakimbo Bridge, Demoudoula Bridge, Kiroti Bridge and Kissosso Bridge. The fifth bridge is planned in the Coyah Prefecture on the outskirts of Conakry and is called the Kassonya Bridge. These bridges will increase access of densely populated neighbourhoods in Conakry that are separated by shallows and rivers. The bridges range from 96 m up to
144 m in length and are accompanied by 13.54 km of road.

The Guinea regulations require a RAP/LRP process, for which consultation is ongoing at this moment, and will result in a stand-alone report, which needs to be approved by the BGEEE as well.
 
The NCEA recommends that the ESIA and RAP/LRP are fully aligned and integrated Specifically, that the ESIA information is made available during the RAP/LRP consultations, and that the ESIA is updated based on the RAP/LRP (consultation) outcomes.

Ce projet de construction de cinq ponts se situe à Conakry, capitale de la Guinée. Le principal objectif de ce projet est d'améliorer l'accessibilité de la ville de Conakry par la construction de cinq ponts et l'amélioration des routes d'accès à ces ponts. Quatre de ces ponts sont prévus dans la Préfecture de Conakry, à savoir : le pont Kakimbo, le pont Demoudoula, le pont Kiroti et le pont Kissosso. Le cinquième pont, le pont Kassonya, est prévu dans la Préfecture de Coyah, en banlieue de Conakry. Ces ponts permettront d'augmenter l'accès à la ville depuis les quartiers densément peuplés qui en sont séparés par des marécages et des rivières. Les ponts mesurent de 96 m à 144 m de long, et nécessitent 13,54 km de routes.

Les réglementations locales d'EE en Guinée nécessite une processus de PAR/PRAE, pour lequel du consultation est fait actuellement, et qui dérivera une rapport autonome. Cette rapport doit etre approuvé par le BGEEE aussi.
 
La CNEE fait la recommendation que l’EIES et les PAR/PRAE seront aligné et intégré. Specificement que le contenu d’EIES sera mis en disposition durant les consultations du PAR/PRAE et que l’EIES sera mis à jour basé sur les résultats de consultation du PAR/PRAE.

Parties concernées

Membres du groupe de travail

Membre
mr J.M.M. Helmer
ms E. De Keyser
mr R. Slootweg

Le président du groupe de travail: ms M.W.J.A. van Gool

Secrétaire technique: mr G.A. Hendriks

D'autres détails

Commencé: 09 jul 2018
Terminé: 23 nov 2018

Catégories

Urban development
Infrastructure
Transport

Pays/région/thème: Guinea

Mise à jour: 25 mrt 2019