099-i. Advisory review ESIA Hydropower Adjarala report - Benin, Togo

The NCEA reviewed the ESIA report for the Adjarala hydropower project on the border between Benin and Togo.

Rapports consultatifs et autres documents

23 sep 2014: Advisory review

Barrage hydroélectrique d'Adjarala, Benin et Togo: avis sur l’examen de la qualité de l’EIES

01 apr 2015: Other

English Summary Adjarala

Informations importantes

As part of the development of the electricity sector, the Communauté Electrique du Benin (CEB) planned to develop hydropower facilities at Adjarala, on the border between Benin and Togo. Most of the reservoir would be located in Togo. According to legislation of both countries, undertaking an Environmental and Social Impact Assessment (ESIA) is required for such a project. the Beninese and Togolese environmental agencies (resp. ABE and ANGE) together asked the NCEA for its opinion on the ESIA which had been submitted by the CEB. The NCEA established a working group and issued an independent review. Based on the ESIA's findings, both environmental agencies gave the project permission under specific conditions. Due to financing issues, the dam still has not been built in 2018.

Parties concernées

Membres du groupe de travail

Membre
mr G. Ale
mr B. Hagin
ms M. Reinders
mr L. Zwarts

Le président du groupe de travail: mr A. van der Velden

Secrétaire technique: mr S.G. Nooteboom

D'autres détails

Commencé: 08 mei 2014
Terminé: 24 sep 2014

Catégories

Energy (renewable)
Hydropower
Infrastructure
Integrated Water Resources Management (IWRM)
Transboundary issues
Environmental and Social Impact Assessment (ESIA)

Pays/région/thème: Benin; Togo

Mise à jour: 27 mrt 2019