History of EIA

Brief description of the history of the EIA system in the country, including when it was introduced and any major milestones in its development.

In the early and mid 1980s, EIA in Bangladesh was mainly donor driven. In the time, environmental issues started to be seen as much more linked to broader development issues and became institutionalised in 1989 with the establishment of the present Ministry of Environment and Forestry. In line with the general recommendations of the Rio Earth Summit, The National Environmental Policy was framed in 1992. This policy required EIA for all new public and private projects. In 1993, the National Environmental Committee headed by the Prime Minister was formed to address environmental issues at the central level. Several guidelines were prepared in 1990s. Key of these guidelines included: Guidelines on Environmental Issues Related to Physical planning in 1992 and Guidelines for Physical Planning of Rural Areas in Bangladesh in1995. These are said to have had little influence on EIA thus ultimately, the Environmental Conservation Act (1995) and the Environmental Conservation Rules (1997) gave formal status to EIA in Bangladesh. Thereafter, the EIA system had been further developed through amendments of the Act and the Rules and the issuance of the Environmental Court Act in 2000.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-7.

Year of introduction of EIA legislation

NB: this field is only meant for the world map. It is a hidden cell that is not published on the website. If available, mention the year when detailed national EIA regulations were issued. If such regulations do not exist and if EIA practice is base

1995

Legal framework for EIA

to the top

Framework/Enabling law

Name of first enabling legislation that sets a framework for EIA.

The Environmental Conservation Act makes mandatory provisions for environmental clearance of all industrial units and projects.

Approving authority of enabling law

Authority that approved the enabling law for EIA.

The parliament has approved the Environmental Conservation Act.

Year of introduction of first national detailed regulation for EIA

Year when when the first national detailed regulation (procedural requirements) through which EIA was operationalized.

Environmental Conservation Rules (1997) provide a procedure for granting environmental clearance under article 7. These rules were issued by the Minister in charge of the environment and forestry.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78.

1997

Recent updates and additions to the EIA legislation

Revisions of the EIA provisions in the enabling law or the national detailed EIA regulation (procedural requirements) are named. The year is listed, and the main changes since the first regulation are mentioned, if available. Also, additional EIA-re

The Environment Conservation Act (1995) has been amended by Act No 12 of 2000 and Act No 9 of 2002. In 2000, the Environment Court Act (Act No. 11 of 2000) which also contains amendments to the Environmental Conservation Act was issued and further amended in 2002.

The Environmental Conservation Rules (1997) were amended in 2002 and 2003.

The website of the Department of Environment indicates that several further amendments have been made recently. The Rules have been amended in 2012, the Environment Conservation Act in 2010, the Environment Court Act in 2010. Additionally ECA rules for public comments have been drafted.
Remark: These amendments and new guidelines are not available in English. Their content could not be considered for this country profile.

Sector specific procedures or regulations on EIA

Any existing sectoral procedural or content regulations are listed here, as well as the authority that issued each.

No information

Guidelines

Any government issued guidelines on EIA (general, or sectoral) are listed here, as well as the authority that issued each. Describe the legal status of the guidelines.

There are EIA-related guidelines, which are not legally binding though. These include: (a) EIA guidelines for Industries by the Department of Environment 1997; (b) EIA guidelines on water sector, prepared under the Flood Action Plan, 1992 and updated in 2003;

As part of the BEISP capacity development programme (2006-2010), DoE has drafted EIA guidelines for several sectors including coal mining, gas, pharmaceuticals, cement factories, water and transport sectors. Most of these guidelines are still in draft but DoE intends to finalize and gazette them.

Moreover, the Water Resources Planning Organization (WARPO) and the Local Government Engineering Department (LGED) have developed their own EIA guidelines.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78 ADB, 2012. Subproject proposal. Strengthening Environmental Impact Assessment System.

Objective of EIA

The objective of EIA as stated in the above described legal basis.

Not clearly specified in the legal basis.

Scope of EIA application

Describes which types of activities require EIA (public and/or private activities; national and/or foreign initiated project; or all such projects)

EIA is required for all activities (private, public and foreign investment) that fall under the category of red projects as stipulated under schedule one of the Environmental Protection Rules.

Exemptions from EIA application

Describes any (groups of) activities identified in the regulation that are exempted from the requirement to do EIA (e.g. military or emergency activities).

No information

Institutional setting for EIA

to the top

Central EIA authority

Is there a central authority in charge of implementing EIA? Is it independent or linked to a higher body (e.g ministry)? What are its tasks related to EIA?

The Department of Environment (DoE) is the responsible body for implementing and enforcing EIA. Under the provision of the Environment Conservation Act, 1995, DoE and its six divisional offices, are authorized to review and approve the EIA reports and to process and issue environmental clearance for all types of industrial units and projects. They are also mandated to formulate environmental guidelines and advise the Government to reject manufacturing processes, materials and substances likely to cause environmental pollution. Other core activities of DoE besides EIA include environmental knowledge management, and enforcement. Within the office of the Director, there is a unit headed by a Deputy Director EIA who coordinates EIA-related services. DoE is the technical arm of the Ministry of Environment and Forest (MoEF) that is responsible for environmental planning and management.

Ahmed R and N Harvey, (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78 Kabir (2012). A critical evaluation of the environmental impact assessment system in Ban

Other key (governmental) parties involved in EIA, and their roles

Lists other key parties (e.g. a review commission, knowledge institute) that have a role in many or all EIAs.

The Ministry of Environment and Forest (MoEF) is the principal Government institution to deal with the environmental activities in Bangladesh. It is the final body for all matters relating to National Environmental Policy and regulatory issues. It plays key roles in planning, reviewing, monitoring and environmental initiatives and ensuring that environmental concerns are properly handled. MoEF supervises the DoE and can also formulate policies and rules.

DoE has constituted a technical committee for the review process comprising of the Director (Technical), Deputy Director (Research), Joint Director (Biodiversity) and Project Coordinator (IDCOL)

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78

Mandate for exemption of EIA obligation

Describes if there is a legal mandate for a competent authority to make exemptions of EIA obligation. And if yes, under which conditions (e.g. national security, disasters or no conditions/when deemed necessary).

The Director General may directly issue an Environmental Clearance, without requiring the mandatory Location Clearance in certain cases. These cases are however not specified.

The Environmental Conservation Rules, 1997 (Article 7-4)

EIA procedure

to the top

Screening

Screening requirement and authority

Describes if a formal screening decision required, and if so, which authority is responsible for this decision. Is this decision published?

Screening is a required step of the EIA procedues and it is done by the DoE.

Screening process

Describes the screening process: steps in screening, the stakeholders involved and outcomes of the process, status of screening advice of different stakeholders, etc. Also describes any prescribed methods for screening. If preliminary EIA's / light EIA's / Initial Environmental Evaluations (IEE) are done in this country and which criteria determine whether a preliminary or a full EIA is requested

The proponent first sends an activity proposal to DoE to form the basis of screening. Screening is based on a list contained in Schedule I of the Environment Conservation Rule (1997). Based on the project features, DoE categorizes the project in any of  4 categories based on location and impact on the environment (a location clearance is required for location and an environmental clearance is required for environmental impacts). These categories include green, orange A, orange B, and red. Projects categorized as green require no location clearence but a environmental clearance. All other categories require a location clearance, and an environmental clearance. Orange A projects requires a layout plan, process flow diagram and outlines of plans for relocation and rehabilitation while green projects do not. The difference between category orange A and B is that category B projects require both an Initial Environmental Examination (IEE) and an EMP for clearance while orange A do not. In addition to the requirement of the orange B category, Red projects require a full EIA.

Once it has decided under which category a project falls, DoE communicates to the proponent if a request for application documents for environmental clearance if needed. The application for the certificate has to be submitted to the concerned divisional officer of the department. A form of such an application is attached in the Environmental Conversation Rules (Form 3).

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78

Provision for sensitive areas

Are specific requirements formulated for environmentally sensitive areas? (e.g. no minimum thresholds, full EIA instead of partial EIA)

There are provisions for sensitive areas. The ECR (1997) gives the government the mandate and guidance in declaring certain areas sensitive. In such cases a full EIA is required.

Contents of the starting document

Describes the required content of the starting document (if any) that the proponent should submit to the competent authority for EIA screening. Mentions if the starting document is published.

For the initial categorization process of the project, an activity proposal has to be sumitted to DoE. Its content is not specified.

Timeline Screening

Maximum number of (working) days allowed between submission of the starting document and the screening decision.

Not specified in legislation

Scoping

Scoping requirement

Is a formal scoping step required as part of the EIA process?

For red category projects the Terms of Reference of the EIA report are prepared by DoE.

Scoping process

Describes who carries main responsibility to undertake scoping and what the roles and responsibilities of the involved parties during the process are. Specifically, is there independent formulation and/or review of the scoping document, approval of the scoping document? Are any methods prescribed, e.g. participation, checklists. What guidance is provided?

After an IEE is approved and the proponent has obtained a Site Clearance Certificate for the project,  the proponent is allowed to begin preparation works for the project. For Red category projects, the DoE prepares a Terms of Reference in conjunction with the proponent which is used by the proponent to prepare an EIA. Scoping mainly involves baseline studies.

Contents of the scoping document

Explains if there are there specific requirements for the content of the scoping document, and if so, what these are.

Apart from the ToR prepared by DoE, other contents for scoping documents are not specified.

Timeline scoping

Number of (working) days for the decision on approval of the scoping document by the competent authority.

The approval of the ToR shall take place within 15 working days from the date of submission.

EIS with flowchart.

Assessment and reporting

Assessment process

Steps and roles of stakeholders in the assessment and status of the input of the stakeholders. Also sets out methods for assessment of the environmental impacts of the activity, if prescribed, and whether the assessment covers environmental, social, economic and/or transboundary effects.

The legal framework does not specify assessment methods.  However, the EIA guidelines for Industries advises use of checklists, matrices networks, overlays, environmental index using factor analysis, cost-benefit analysis and simulation modelling. It also suggests methodologies on impact evaluation, prediction and identification of mitigation measures. The guidelines suggest public participation. The public and NGOs are invited (discretionary) to give their views on the draft EIA report that is produced.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78

Contents of the EIA report

Explains what should be contained in the EIA report. Specifies if a potential Environmental Management Plan is part of the EIA report or if it is a separate document that contributes to the EIA process.

The proponent is required to address the following: (i) baseline studies; (ii) impact identification; (iii) impact prediction; (iv) impact evaluation; (v) mitigation measures; (vi) monitoring program; (vii) special studies (for example risk assessment, rehabilitation study etc)

Review

Review process

Overview of the review process, including: steps in the process and roles of the stakeholders, status of the input of the stakeholders. Is the process open to public? Review method: internal review, external review, panel/commission (permanent or temporary), are the review results documented? Are the review criteria general or case by case? Are the review results documented? Is a potential review

Review is internal as the DoE is responsible for it. DoE has constituted a technical committee comprising of the Director (Technical), Deputy Director (Research), Joint Director (Biodiversity) and Project Coordinator (IDCOL). The review criteria are not specified (to be confirmed) .

There are no specific procedural steps for conducting and reviewing EIA in the ECA. Additionally, guidelines for review of non-industrial projects are non-existent and the review process for such projects is said to be on an ad hoc basis. However, the industrial and water sector guidelines give suggestions on reviewing EIA report which the review committee of DoE follows. In general, the DoE offices in each of the six divisions receive applications and issue Environmental Clearance Certificates for proposed investments within that division. The divisional offices verify supporting documents and pass it on to the divisional head, who assigns an inspector for follow-up. For green and orange A category projects, the inspector submits his report to the divisional head who makes a decision within three days of receiving the report. Files for orange B and red category projects are sent to the Senior Chemist/Assistant Director for checking. The files are then forwarded by the divisional office to the Environmental Clearance Committee of the DoE in Dhaka, and then passed to the Director General of the DoE for final clearance. Most Environmental Clearances issued by DoE are from the Dhaka divisional office.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78 and World Bank 2006

Review expertise

Describes if the EIA is checked by external parties, and if so to what extent these represent required disciplines/expertise. Also sets out if measures have been taken to ensure that reviewers are impartial?

EIA experts can participate in the review process, if invited by DoE.

Kabir SMZ, (2012). A critical evaluation of the environmental impact assessment system in Bangladesh using a holistic approach. University of Newcastle.

Timeline Review

Number of (working) days for review of the EIA by the competent authority.

Article 11 of the Environmental Conservation Rules prescribes that for projects under category Red, the EIA report shall be approved or the application for an environmental clearance certificate shall be rejected within 60 working days from when the EIA report was submitted.

Decision-making

Integration of EIA into decision-making

Describes what kind of decision-making processes the EIA is intended to support. We look specifically at the decision on EIA approval, and how this relates to envirionmental approval for the project, and other project approval decisions (permits) needed before a project can proceed. This category describes which decisions are influenced by EIA and how they are linked to each other.

The EIA process is linked to several content decisions in Bangladesh. The conduction of a full EIA and thus an EIA approval decision is required for Red category projects only, other category projects (Green, Orange A and B) do not require an EIA report. For these projects, firstly a Site Clearance Certificate has to be obtained. Once this certificate has been issued, the proponent shall submit the EIA report for approval. Following the EIA approval, the proponent shall apply for an Environmental Clearance Certificate. The application for such an Environmental Clearance Certificate contains among other documents the EIA report, the Environmental Management Plan and a no objection certificate (approval form the local authority). Thereafter, a decision on the issuing of the Environmental Clearance Certificate is taken. Without such an certificate, the proponent shall not have gas line connections and shall no trial production in case of an industrial unit, and in other cases shall not start operation of the project. It is unclear if the issuing of the Environmental Clearance Certificate is a project approval at the same time.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-78 Environmental Conservation Rules (1997)

Competent authority

Describes which authority/authorities is/are responsible for each of the main decision-making processes on EIA (EIA approval, environmental approval and/or project approval). It is explained if those decisions are taken by the same or different authorities.

The Director General of the DoE takes the decision on the issuing of the Environmental Clearance Certificate.

Environmental Conservation Act (1995)

Decision justification

Sets out requirements for justification of the consideration of the EIA information in decision-making (on EIA approval, environmental approval and/or project approval).

According to the Environmental Conservation Rules (1997), when an application for an environmental clearance certificate is rejected, appropriate reasons need to be mentioned.

Environmental Conservation Rules 1997 (Article 7 (11, 14)

Timeline decision-making

Maximum number of (working) days available to the competent authority to make the EIA based decision (EIA approval, environmental clearance and/or project approval).

According to the Environmental Conservation Rules (1997), the decision on the issuance of the environmental clearance certificate has to be taken within 60 days from the application for the certificate onwards and thus after the EIA report has been approved.

Monitoring, Compliance and Enforcement

Compliance monitoring

Is compliance monitoring required to check if the project is implemented as described in the EIA documents and/or if mitigation of environmental impacts complies with applicable standards and other measures set out in the EIA documents? Who is responsible for ensuring compliance? How does this authority ensure compliance (for example, through inspections)? And what requirements are there for the p

Clear legal provisions for EIA compliance and monitoring are absent. It is mentioned in the EIA rules that an EMP is required for orange B and red category projects. It needs to be prepared by the proponent and submitted as part of the application of location and environmental clearance. Monitoring is said to be conducted on an ad-hoc basis and there are no specific provisions for green and orange A category projects.

Environmental Conservation Rules (Article 7), World bank 2006

External monitoring

Are there monitoring requirements that involve external parties, such as citizen monitoring (for example, through a complaints procedure), or third party auditing?

No information.

Non-compliance penalties

Are there penalties that the authority responsible for compliance can apply if environmental conditions are not met? What are these? (for example, fines, suspension of license)

Suspension of clearance is possible. The ECA provides that failure to comply with any part of it may result in the punishment of a maximum of 5 years imprisonment or a maximum fine of 100,000Tk (1,460USD) or both.

Environmental Conservation Act (1995), article 15, 16

EIA evaluation

Are there any requirements to monitor if the impacts in reality are as they were predicted in the EIA, with the purpose of evaluating the EIA itself and improving future EIA practice?

No information.

Payment system

Is the proponent required to pay a fee when applying for an EIA? Is this fee linked to a permitting fee, or separate? If yes, when is this paid and to whom (to the agency that issues the license or to a central agency)?

The proponent pays a fee to obtain the environmental clearance certificate, and a fee to renew the certificate once a year for  green category projects and once every three years for the other categories of projects. The fees are paid to the Director General, DOE. The fee for issuance or renewal of the environmental clearance certificate depends on the amount invested in the project. For example, if the investment is between Tk 100,000 (approx 1500 USD) and 500,000Tk the fee for the environmental clearance certificate is 1,500 Tk. Certificate renewal costs one-fourth of the certificate fee. (NB: 1USD=79Tk in Feb 2013).

Environmental Conservation Rules, 1997 (Schedule 13)

Public participation

Public participation requirements for EIA process stages

Describes for which of the EIA process stages public participation is required.

There are no legal requirement for public consultation during EA process or even for provision of information to affected people. The Environmental Conservation Rules do not mention public nor community. However, different guidelines such as the water sector guidelines suggest public participation at the early stage of EIA study and recognise the need to consider socio-cultural, physical and biological impacts. According the EIA guidelines for industries, opportunities for the public to participate are under the discretion of the Director General of DOE.

Ahmed R and N Harvey (2004). Evolution of EIA procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1. Pgs 63-7

Public participation guidance

Has any guidance on participation been provided?

No Public participation manual exists, but the guidelines for EIA of the water sector development 1992 put a great emphasize on public participation.

Remark: The website of DoE mentions that ECA Rules for Public Comments have been drafted. These are not available in English though and could not be considered for the content of this profile.

Legal recourse

Possibilities for appeal

What are the legal recourse options to challenge EIA decisions are provided for within the legal framework?

The Environmental Courts Acts of 2000 establishes Environmental Appeal Courts for environmental offences (in general). Appeals can also be made to specialised magistrate courts where environmental laws provide for a penalty of an imprisonment not exceeding 2 years or a fine not exceeding 10,000Tk (145USD) or both.

Environmental Courts Act, 2000 (article11)

Decisions that can be appealed

Which EIA decisions can be appealed?

The decision on the issuance of an Environmental Clearance Certificate can be appealed (to be confirmed).

Who can appeal

Who can make an appeal (in other words, has legal standing)?

Any person (within 30 days from the date of issuance of the notice). An appeal fee of 1000 Taka is charged to any appellant including the general public.

Environmental Conservation Rules, 1997 (Article 9)

EIA practice

to the top

Annual no. of EIAs

Gives an estimation for the number of full EIAs that are produced annually in this country.

In 2000-2001 DoE processed almost 1,300 environmental clearance certificates.

Central EIA database

Is there a central database or library where information on EIAs is kept (i.e. where all EIAs are registered and/or copies are archived). If so, what is kept there and is this information publicly accessible?

No information

Practice reviews

Any EIA practice review studies that have been done (by governmental agencies or others) are listed here. Where relevant, links to studies are included, and the main conclusions of the studies are summarised.

• Ahmed R and N Harvey (2004). Evolution of EIA  procedures and Practice in Bangladesh. Journal of Impact Assessment and Project Appraisal. Vol 22 No. 1, Pgs 63-78.

• Momtaz Salim (2001) Environmental Impact Assessment in Bangladesh: A Critical Review. Environmental Impact Assessment Review.

Accreditation of consultants

Is there and accreditation system operational in the country to certify consultants to do EIAs?

No information.

Professional bodies

Professional bodies relevant to EIA practice in the country, such as EIA Associations, Environmental Expert Associations, etc are listed here.

• NEAB (National EIA Association of Bangladesh): An association of planners, practitioners and enforcement agencies that has been working to create awareness of EIA in all sectors of Government planning. It has assisted in the development and extension of EIA, prescribing a code of conduct for EIA professionals, building national capability and establishing a liaison between EIA practitioners and policy-makers in Bangladesh.                                                                                                             

  • BELA (Bangladesh Environmental Lawyers Association): Has played a role in the introduction of public interest litigation cases to higher courts (the High Court and the Supreme court). An important achievement won by BELA in response to its appeal was the Supreme Court decision in 1998 to grant citizens and NGOs the right to enforce environmental laws.                                                         

  • FEJB (Forum of Environmental Journalists, Bangladesh); Has been particularly effective in creating environmental awareness, and a number of State of the Environment Reports have been produced by civil society organizations.

Non-governmental EIA guidance

Lists any EIA manuals and good practice publications (including checklists, case studies) that have been published by parties other than government.

Guide to the Environmental Conservation Act 1995 and Rules 1997, Bangladesh Center for Advanced Studies, 1999.

Capacity development

Ongoing training programmes (including professional and academic training) and major training events held in the past (with focus on recent events) are mentioned here.

Capacity development for Environmental Assessment Project (CDEAP): Funded by Directorate General for International Cooperation (DGIS-Netherlands) in cooperation with the Dutch EIA Commission, the project started in January 1999 and had a mandate to enhance the capacity for environmental assessment (EA) in South Asian countries (Bangladesh, Bhutan, India, Nepal, Pakistan and Sri Lanka). The main objective is to establish and strengthen National Environmental Assessment Associations (NEAAs) and a regional organization, the South Asian Regional Environmental Association (SAREEA). The Regional Environmental Assessment Programme (REAP) of IUCN’s Asia Regional Directorate was the implementing agency for the project.

The Bangladesh Environmental Institutional Strengthening Project (BEISP) was implemented by DoE from 2006 until 2010.

In June 2012 the Asian Development Bank has proposed a subproject for Bangladesh on the strengthening of the EIA system and its implementation practices under the regional technical assistance 7566: 'Strengthening and Use of Country Safeguard Systems'.

EIA links

to the top

Links to laws/regulation

Any relevant links to laws or regulations are included here.

Links to Laws on the website of MoEF: http://www.moef.gov.bd/html/laws/laws.html

Environmental Conservation Act (1995)

Environmental Conservation Rules (1997)

Environment Court Act (2000)

Other relevant links on EIA

Any other relevant links (for example to country specific guidance documents) are included here.

EIA information on the website of the Department of Environment: http://www.doe-bd.org/eia.html

Study of the Bangladesh Engineers' Association on the EIA system in Bangladesh